ATC19 — AMAN/DMAN Integration

Integrated Arrival and Departure management aims at increasing airport and TMA throughput, resilience and predictability by improved co-ordination between En-Route/Approach, local ATC and airports.

DMAN provides optimum departure sequence based on information provided by airport operator, airlines and ATC.

Similarly, AMAN calculates the optimum arrival flow to the airport. Integration of runway sequence, respecting AMAN and DMAN constraints, allows for optimum utilisation of runway.
Where this integration interferes with the 180 nautical miles (or shorter distance as indicated in Implementation Objective ATC15.2 – Arrival Management Extended to En-route Airspace Family 1.1.1) requirement for extended AMAN, the system has to be tuned to allow as large horizon as possible.

System requirements:

• Integration of departure and arrival flows are done by integrating existing AMAN and DMAN functions where runways are operated in mixed mode.
• AMAN and DMAN systems shall be able to share data to be included in their planning algorithms calculating arrival and departure flows.
• The integration of AMAN and DMAN must be based on the optimised pre-departure sequence and interfaces with airport CDM systems.
• Controller Working Position (CWP) needs to support the display of AMAN/DMAN overlapping sequences.

NOTE FOR MILITARY AUTHORITIES: It is the responsibility of each military authority to review this Objective IN ITS ENTIRETY and address each of the SLoAs that the military authority considers RELEVANT for itself. This has to be done on top and above of the review of "MIL" SLoAs which identify actions EXCLUSIVE to military authorities.

Edition
2022
Stakeholders
Air Navigation Service Provider / Airport Operator
Type
CP1
Scope
Airport
Status
Active

Context

Related Elements

Applicability Area(s) and Timescales

Applicability Area 1:
See list of airports in MP Level 3 Implementation Plan - Annexes
Applicability Area 2:
See list of airports in MP Level 3 Implementation Plan - Annexes
Timescales From By Applicable to
Initial Operational Capability 01-01-2021 - Applicability Area 1 + Applicability Area 2
Full Operational Capability / Target Date - 31-12-2027 Applicability Area 1 + Applicability Area 2

Links to SESAR Solutions

Links to PCP ATM Sub-Functionalities

ICAO Block Modules: No associated data

References

Applicable legislation
Regulation (EU) 2021/116 on the establishment of the Common Project One
Applicable ICAO Annexes and other references
None
Deployment Programme 2022
Family 1.2.1 - AMAN/DMAN Integration
Operating Environments
Airport
Terminal Airspace

Expected Performance Benefits

Safety
-
Capacity
-
Operational efficiency
Contribution to Predictability; increase in resilience.
Cost efficiency
-
Environment
The coupling of AMAN with DMAN has been shown to save departure fuel and improve local air quality due to a reduction in the taxi-out time during peak traffic (up to 7% savings in taxi-out fuel)
Security
-
  Code Title From By Related Enablers
 
ASP01 Couple AMAN and DMAN systems
  • 01-01-2021
  • 31-12-2027
 
ASP02 Establish Bilateral Agreements
  • 01-01-2021
  • 31-12-2027
 
ASP03 Upgrade CWP to incorporate the information from integrated AMAN/DMAN
  • 01-01-2021
  • 31-12-2027
 
ASP04 Safety assessment
  • 01-01-2021
  • 31-12-2027
 
ASP05 Training
  • 01-01-2021
  • 31-12-2027
 
ASP06 Operational use
  • 01-01-2021
  • 31-12-2027
 
APO01 Upgrade system to incorporate AMAN/DMAN information
  • 01-01-2021
  • 31-12-2027
 
APO02 Establish Bilateral Agreements
  • 01-01-2021
  • 31-12-2027
 
APO03 Safety assessment
  • 01-01-2021
  • 31-12-2027
 
APO04 Training
  • 01-01-2021
  • 31-12-2027
 
APO05 Operational use
  • 01-01-2021
  • 31-12-2027
Code Dates
 
1999 99
2000 00
2001 01
2002 02
2003 03
2004 04
2005 05
2006 06
2007 07
2008 08
2009 09
2010 10
2011 11
2012 12
2013 13
2014 14
2015 15
2016 16
2017 17
2018 18
2019 19
2020 20
2021 21
2022 22
2023 23
2024 24
2025 25
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
ATC19
 
20210101_20271231
ASP01
 
10%
20210101_20271231
ASP02
 
14%
20210101_20271231
ASP03
 
7%
20210101_20271231
ASP04
 
7%
20210101_20271231
ASP05
 
7%
20210101_20271231
ASP06
 
7%
20210101_20271231
APO01
 
14%
20210101_20271231
APO02
 
13%
20210101_20271231
APO03
 
13%
20210101_20271231
APO04
 
13%
20210101_20271231
APO05
 
13%
20210101_20271231

Supporting Material

Title Related SLoAs

SDM - Standardisation and Regulation support to CP1 deployment 2021, Deliverable D1.1.1 07/2021

https://www.sesardeploymentmanager.eu/publications/deployment-programme

APO01, APO02, APO03, APO04, ASP01, ASP02, ASP03, ASP04, ASP05

Consultation & Approval

Working Arrangement in charge
Airport Operations Team (AOT)
Outline description approved in
-
Latest objective review at expert level
-
Commitment Decision Body
Provisional Council (PC)
Objective approved/endorsed in
05/2019
Latest change to objective approved/endorsed in
-